Question: 5 1 0 - 5 1 5 3 . The total capital investment for a hydrometallurgical plant of zinc production is Rs . 1 0

510-515
3. The total capital investment for a hydrometallurgical plant of zinc production is Rs.10Cr and the plant produces 4,000 tons of products annually. The selling price of zinc product is Rs,0.33 Lakhs/ton. The working capital amounts to 16% of total capital investment (TCI). For the imestment, which is made by company funds, no interest is charged. Raw material (zinc concentrate) costs for the zinc product are Rs.0.036 Lakhs/ton, labor Rs.0.032 Lakhs/ton, utilities Rs.0.02 Lakhs/ton and packaging Rs.0.0032 Lakhs/ton. Distribution costs are 4% of the total production costs (TPC). Estimate the following:
A. Manufacture cost per ton of product.
B. Total production cost per year
C. Profit per ton of product after taxes.
D.% ROI
E. Payout time
 510-515 3. The total capital investment for a hydrometallurgical plant of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!