Question: 5 . 1 6 At 8 : 0 0 A . M . there are 1 0 vehicles in a queue at a toll booth
At : AM there are vehicles in a queue at a toll booth and vehicles are arriving at a rate of lambda tt Beginning at AM vehicles are being serviced at a rate of and mu t are in vehicles per minute and t is in minutes after : AM Assuming DD queuing, what is the maximum queue length, and what would the total delay be from : AM until the queue clears? Draw DD