Question: 5. (10 Points) Given the following information about a project, calculate the earned value, cost variance, schedule variance, and cost performance index for weeks one

 5. (10 Points) Given the following information about a project, calculate

5. (10 Points) Given the following information about a project, calculate the earned value, cost variance, schedule variance, and cost performance index for weeks one and two. Calculate the Estimate to Completion. Make a plot of planned actual, and earned values. Show the Estimate At Completion on the plot. Week Week Week Ten One Two (End) Rate of performance Planned value Actual cost 140% $20,000 $28,000 65% $32,000 $27,000 $280,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!