Question: 5. (10 Points) Given the following information about a project, calculate the earned value, cost variance, schedule variance, and cost performance index for weeks one

5. (10 Points) Given the following information about a project, calculate the earned value, cost variance, schedule variance, and cost performance index for weeks one and two. Calculate the Estimate to Completion. Make a plot of planned actual, and earned values. Show the Estimate At Completion on the plot. Week Week Week Ten One Two (End) Rate of performance Planned value Actual cost 140% $20,000 $28,000 65% $32,000 $27,000 $280,000