Question: 5 2 . You are a new project manager who has never managed a project before. It would be BEST in this situation to rely

52. You are a new project manager who has never managed a project before. It would be
BEST in this situation to rely on _____ during planning to improve your chance of success.
A. Your intuition and training
B. Stakeholder analysis
C. Historical information
D. Configuration management
53. Typically, the signing of a project charter is the responsibility of:
A. Project Sponsor
B. Senior Management
C. Project Manager
D. Project stake-holders
54. Tom is working as a Project Manager at StateEx, which is a nationwide logistics company.
Tom manages a project to optimize the vehicles location, pickup points, and routes for
effective and efficient delivery. Victoria, one of the project team members, emails you that
she did not understand her tasks clearly. What should you do next?
A. Response via email that he should reread the project scope document.
Service PrepaPMP February-July 2024 Page 25 on 32
B. Call Victorias functional manager and confirm again if she is qualified to work on the
project
C. Arrange a one-on-one meeting with Victoria and try to understand what is not clear to her
D. Raise this issue in the next team meeting and ask the team to clarify the tasks for Victoria
55. The Output of Direct and Manage Project Execution process is:
A. Project plan
B. Preliminary scope statement
C. Preliminary cost estimate
D. Deliverable

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!