Question: 5. (20 points) Use Coffman-Graham algorithm to construct a schedule for the following jobs on 2 identical and parallel machines. Each job has a processing

5. (20 points) Use Coffman-Graham algorithm to construct a schedule for the following jobs on 2 identical and parallel machines. Each job has a processing time of 1 unit