Question: 5 7 . Project management process groups have all of the following characteristics except: A . All of the process groups are needed on all
Project management process groups have all of the following characteristics
except:
A All of the process groups are needed on all projects and all of their interactions
apply to each phase of a project as well as the overall project.
B The process groups are seldom onetime, discrete events; they are overlapping
activities that occur throughout the project.
C Where a project is divided into phases, the process groups are invoked as
appropriate.
D The process groups are linked by the outputs they produce