Question: 5. (8 Marks). Here is a precedence requirements for a construction project Job Predecessor Task time (weeks) A - 2.0 B A 1.5 C B
5. (8 Marks). Here is a precedence requirements for a construction project
| Job | Predecessor | Task time (weeks) |
| A | - | 2.0 |
| B | A | 1.5 |
| C | B | 3.0 |
| D | A | 1.0 |
| E | D | 0.5 |
| F | C & E | 2.0 |
| G | F | 0.5 |
| H | A | 0.5 |
| I | H | 1.0 |
| J | G & I | 1.0 |
| K | H | 0.5 |
| L | K | 0.5 |
| M | J & L | 1.0 |
| N | M | 0.5 |
| P | N | - |
a) (2 mark) Draw the project network
b) (5 marks) Calculate the ES, EF, LS and LF for all activity with proper procedures.
c) (1 mark) Calculate the free slack for all activity in this project network and put it in a table