Question: 5 Additional Algo 4-8 Add one worker Loans are evaluated in a process with two resources. The first resource has a capacity of 35 loans
5 Additional Algo 4-8 Add one worker Loans are evaluated in a process with two resources. The first resource has a capacity of 35 loans per hour. The capacity of the second resource is 3.2 loans per hour. The first resource has to workers and the second resource has 12 workers. One additional worker is hired who is as productive as the current workers Book Instruction: Round your answer to three decimal places What is the new capacity of this process? loans per hour