Question: 5 - As the project manager, you are leading a brainstorming session with key stakeholdiers to identify project risks. Once the project risks are determined,

5- As the project manager, you are leading a brainstorming session with key stakeholdiers
to identify project risks. Once the project risks are determined, you immediately
proceed to nominate different team members as risk owners and assign them the tankic
of developing individual risk response plans.
Have you properly conducted risk management planning?
a) No, you should be the one developing the risk response plans as you are ultimately
responsible for the outcomes of the project.
b) Yes, the risk response plans are an output of the Identify Risks process and should be
developed right after the risks have been identified.
c) No, before assigning risk responsibility to team members, you need to assess each
risk's probability of occurrence and its impact.
d) Yes, the team members should be assigned responsibility for a risk as soon as possible
and tasked with creating a risk response plan.
 5- As the project manager, you are leading a brainstorming session

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!