Question: 5 . d2 E.1 H,3 3 6 A,4 7 1.4 1 0,1 B.2 C.7 F.3 G.2 2 5 d1 Based on the above PERT diagram,

5 . d2 E.1 H,3 3 6 A,4 7 1.4 1 0,1 B.2 C.7 F.3
5 . d2 E.1 H,3 3 6 A,4 7 1.4 1 0,1 B.2 C.7 F.3 G.2 2 5 d1 Based on the above PERT diagram, determine the project completion time. A 8 weeks B. 10 weeks C. 12 weeks D. 14 weeks 6 Node EET 1 0 0 2 2 5 3 4 5 6 7 4 8 10 14 22 4 8 13 14 22 LET The above table shows the EET and LET for all events in a project. Identify the critical path for the project. A. 1,2,5,6,7 B. 1,2,3,5,6,7 C. 1,3,4,5,6,7 D. 1,3,4,6,7