Question: 5. Draw the project network for the project given in this table. Find the critical path, EST, EFT, LST, LFT for each activity in this

5. Draw the project network for the project given in this table. Find the critical path, EST, EFT, LST, LFT for each activity in this project network. What is the earliest finish time of this project? Calculate the total slack and free slack for each activity
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts