Question: 5. During Year 1, Gates Corp. started a construction job with a total contract price of $4,000,000. The job was completed on December 15, Year
5. During Year 1, Gates Corp. started a construction job with a total contract price of $4,000,000. The job was completed on December 15, Year 2. Additional data are as follows: Year 1 Year 2 Actual costs incurred during the year $990,000 $1,200,000 Estimated remaining costs 1,210,000 Billed to customer 1,600,000 2,400,000 Received from customer 1,200,000 2,400,000 A. Prepare the journal entries necessary for Year 1 using the percentage of completion method. B. What amount of gross profit will be recognized in Year 1 using the completed-contract method
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
