Question: ( 5 ) Four jobs, A , B , C , and D have to be done on five machines, M 1 , M 2

(5) Four jobs, A, B, C, and D have to be done on five machines, M1, M2, M3, M4, and M5in the operation sequence given below. Draw a Gantt chart to show the scheduling of these jobs based on least slack rule. (10 pts bonus)
\table[[Jobs,Operations,Due Date],[1,2,3,4,5],[machines - hours],[A,M3-3,M1-2,M2-6,M5-3,M4-3,25],[B,M2-5,M4-4,M1-5,M3-4,M5-3,30],[C,M3-4,M4-5,M2-5,M5-2,M1-5,28],[D,MS-2,M3-3,M2-4,M1-5,M4-6,32]]
 (5) Four jobs, A, B, C, and D have to be