Question: 5). If you miscalculated the Slack Time (L-E start and L-E finish) and 2 critical activities are missing on your critical path, which of the

5). If you miscalculated the Slack Time (L-E start and L-E finish) and 2 critical activities are missing on your critical path, which of the followins will happen?
A). A 50% chance that the project's completion dates will be shorter than correct ones;
B). A 99% chance of on-time completion date will be longer than the correct one;
C). The project's standard deviation will become larger; thus, the number of standard deviations (Z score) the target date lies from the mean will become smaller;
D). On the project completion times' normal probability distribution curve, the time between your 99% chance vs. 50% chance completion date will be shorter; t
E). The project will have more non-critical ativities than expected.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!