Question: 5). If you miscalculated the Slack Time (L-E start and L-E finish) and 2 critical activities are missing on your critical path, which of the
| 5). If you miscalculated the Slack Time (L-E start and L-E finish) and 2 critical activities are missing on your critical path, which of the followins will happen? | |||||||
| A). A 50% chance that the project's completion dates will be shorter than correct ones; | |||||||
| B). A 99% chance of on-time completion date will be longer than the correct one; | |||||||
| C). The project's standard deviation will become larger; thus, the number of standard deviations (Z score) the target date lies from the mean will become smaller; | |||||||
| D). On the project completion times' normal probability distribution curve, the time between your 99% chance vs. 50% chance completion date will be shorter; t | |||||||
| E). The project will have more non-critical ativities than expected. |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock