Question: 5 . In the network below: Activity Duration IPA Workers A 6 - 2 B 2 - 3 C 9 - 3 D 4 A

5. In the network below:
Activity Duration IPA Workers
A
6
-
2
B
2
-
3
C
9
-
3
D
4
A, B
3
E
7
B
4
F
5
D
2
G
10
D, E
3
H
8
C, F, G
1
I
3
C, G
2
J
2
H, I
2