Question: 5 . In the network below: Activity Duration IPA Workers A 6 - 2 B 2 - 3 C 9 - 3 D 4 A
In the network below:
Activity Duration IPA Workers
A
B
C
D
A B
E
B
F
D
G
D E
H
C F G
I
C G
J
H I
Manually level your resources with the maximum limit of workers per day. Also, improve resource daily usage start low, increase the resource usage gradually till they peak around the middle of the project, then gradually decrease them towards the end of the project.