Question: 5 jobs ( a , b , c , d , e ) arrive in the given order and have the job times 5 ,

5 jobs (a, b, c, d, e) arrive in the given order and have the job times 5,6,2,4,3 days and are due 10,8,12,9,7 days from now respectively. sequence the jobs according to the spt rule and then compute the average flow time in days, as well as average delays for all the jobs in that sequence