Question: 5. Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project and the requirements for recognizing
5.
Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project and the requirements for recognizing revenue over time are met. The total estimated cost of the project is $4,000,000 and the following information is available:
| ($ in thousands) | Year 1 | Year 2 | Year 3 | ||||||||
| Costs incurred | $ | 1,000 | $ | 1,500 | $ | 1,250 | |||||
| Estimated completion costs | $ | 3,000 | $ | 1,500 | $ | 0 | |||||
| Billings | $ | 750 | $ | 1,750 | $ | 2,500 | |||||
| Cash collected | $ | 500 | $ | 1,500 | $ | 3,000 | |||||
Assuming that revenue is recognized over time, how much income is recognized in Year 3?
Multiple Choice
-
$625,000
-
$1,250,000
-
$1,000,000
-
$375,000