Question: 5. Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project and the requirements for recognizing

5.

Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project and the requirements for recognizing revenue over time are met. The total estimated cost of the project is $4,000,000 and the following information is available:

($ in thousands) Year 1 Year 2 Year 3
Costs incurred $ 1,000 $ 1,500 $ 1,250
Estimated completion costs $ 3,000 $ 1,500 $ 0
Billings $ 750 $ 1,750 $ 2,500
Cash collected $ 500 $ 1,500 $ 3,000

Assuming that revenue is recognized over time, how much income is recognized in Year 3?

Multiple Choice

  • $625,000

  • $1,250,000

  • $1,000,000

  • $375,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!