Question: 5. Organise the tasks assuming the following task sequences: First, you have to define the software scope. When you finalise, the core required resources, you
5. Organise the tasks assuming the following task sequences: First, you have to define the software scope. When you finalise, the core required resources, you can conduct the needs analysis and draft preliminary specifications. You can start the development tasks after you have finalised the software design. Five days after the start of the code development task, you can start unit testing and documentation. Make sure that integration testing does not begin until the unit testing has taken place. Simultaneous to software development, you can start training. The Pilot task can start after testing is finished