Question: ( 5 points ) Assume you are the project manager for the Tidal 2 software project. You have been asked to calculate the expected cost

(5 points) Assume you are the project manager for the Tidal 2 software project. You
have been asked to calculate the expected cost for the project. Your company's
database indicates that developers can handle eight function points each
person-month, and that the cost per developer at your firm is $7,000 per month. You
and your team of five developers have come up with the following requirements:
Using the "complexity weighting" scheme shown in Table 5.2 and the information
provided, calculate the total number of function points, the estimated cost and the
estimated duration of the Tidal 2 project.
 (5 points) Assume you are the project manager for the Tidal

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!