Question: 5 points For a given Master Production Schedule item... Week O Projected On-Hand is 140 units Week 1 Forecast is 60 units Week 1 Booked

5 points For a given Master Production Schedule
5 points For a given Master Production Schedule item... Week O Projected On-Hand is 140 units Week 1 Forecast is 60 units Week 1 Booked Orders is 65 units What is Week 1 Projected On-Hand? Just enter the number) Type your answer. Previous Next