Question: 5 . Use a Scheduled Graph to level load the following PERT diagram ( people ) Act Imm Pred Time Resources A - 2 1

5. Use a Scheduled Graph to level load the following PERT diagram
(people)
Act Imm Pred Time Resources
A
-
2
1
B
-
3
3
C
-
2
2
D
B
5
1
E
A,D
3
1
F
B
2
1
G
C
4
2
a. What is the critical path?
b. How many people can you keep employed for the duration of this project?