Question: 5 What elements are included in a project manager's code of ethics? Responsibility Respect and Fairness Honesty All of the above Project software that is

5 What elements are included in a project manager's code of ethics? Responsibility Respect and Fairness Honesty All of the above Project software that is a tool for scheduling activities and setting the schedule baseline is what type of software? Document management software Scheduling software Issue tracking software Collaboration software 7 Leaders who are dedicated to making the jobs of their team members easier are what type of leader? Democratic Servant leader Laissez-faire Transformational leader 8 According to Human Synergistic, what is the highest performing organizational culture? Aggressive/Defensive Style Democratic Style Constructive Style Passive/Defensive Style