Question: 5) You are choosing between two projects, but can only take one. The cash flows for the projects are given in the following table: 3

5) You are choosing between two projects, but can only take one. The cash flows for the projects are given in the following table: 3 4 0 -50 -100 L 1 25 20 2 20 40 B 50 60 a. What are the IRRs of the two projects? Use an excel spread sheet b. If your discount rate is 5%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently