Question: 55. A project team has run into an issue with a vendor who is known for a lack of quality. The project manager must ensure
55. A project team has run into an issue with a vendor who is known for a lack of quality. The project manager must ensure that the quality problem is addressed appropriately. What should the project manager do to start the issue resolution process? A. Meet with the vendor and request corrective actions. B. Engage the test team to improve the quality. C. Review the risk register and follow the response strategy. D. Update the risk register and document any corrective actions