Question: 55. During the Management Problem Solving workshop, the System Architect notices that one team has raised the risk of not finishing a Feature before the

55. During the Management Problem Solving workshop, the System Architect notices that one team has raised the risk of not finishing a Feature before the end of the PI. What decision should the management team make to help the Program complete the Feature within the PI? Ensure the Feature is properly measured against revenue and profitability Assign the Feature to another team Resize the stories for the team Negotiate a reduction in scope of the Feature