Question: 6 . 1 . Draw the logic network and perform the CPM calculations for the schedule shown next. Find the duration and mark the critical
Draw the logic network and perform the CPM calculations for the schedule shown next. Find the
duration and mark the critical path. Use beginningofday convention.
Activity Duration IPA
A
B A
C A
D B
E B C
F B C
G D E