Question: 6 . 1 . Draw the logic network and perform the CPM calculations for the schedule shown next. Find the duration and mark the critical

6.1. Draw the logic network and perform the CPM calculations for the schedule shown next. Find the
duration and mark the critical path. Use beginning-of-day convention.
Activity Duration IPA
A 5-
B 8 A
C 6 A
D 9 B
E 6 B, C
F 3 B, C
G 3 D, E