Question: 6 150 200 150 100 250 Jon hand inventory Consider the following MRP. The lot sizing technique is EOQ. EOQ 0 1 2 Gross requirements

6 150 200 150 100 250 Jon hand inventory Consider
6 150 200 150 100 250 Jon hand inventory Consider the following MRP. The lot sizing technique is EOQ. EOQ 0 1 2 Gross requirements 1 100 150 Scheduled receipts 0 200 50 Net requirement 100 O 150 Planned receipts 300 0 300 Planned orders 300 O 300 Lead time = 0, Safet Stock = 0, EOQ = 300 0 0 100 300 300 What is the net requirement for period 77 O A, 200