Question: 6 2 2 des Compressing activities on a project with a sensitive project network will: Multiple Choice Increase risk of delaying the project. Improve cost
des Compressing activities on a project with a sensitive project network will: Multiple Choice Increase risk of delaying the project. Improve costtime crashing success. Reduce scheduling flexibility. Increase risk of delaying the project and reduce scheduling flexibility. Increase risk of delaying the project but improve costtime crashing success.