Question: 6 2 points A project manager is creating a work breakdown structure for her project. In the work break down structure, the lowest level of
points
A project manager is creating a work breakdown structure for her project. In the work break down structure, the lowest level of the breakdown for the project manager is called:
Work package
Task
Cost account
Activity