Question: 6. (20 points) Consider the following project activities: Duration (weeks) Activity Predecessor Optimistic Most Likely A - 1 2 B A 2 3 C A

6. (20 points) Consider the following project6. (20 points) Consider the following project

6. (20 points) Consider the following project activities: Duration (weeks) Activity Predecessor Optimistic Most Likely A - 1 2 B A 2 3 C A 1 3 D B 3 6 E C 2 3 A 4 5 3 4 1 2 2 4 FGH I E, F D G, H Pessimistic 4 7 5 9 7 7 8 3 6 d. Calculate the slack for each activity. e. Identify all activities on the Critical Path. f. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score)