Question: 6) [25 points] For the network below: a. [5points] Calculate the schedule for the network in question 2 with positive finishstart lags. Lag Trine deby

 6) [25 points] For the network below: a. [5points] Calculate the

6) [25 points] For the network below: a. [5points] Calculate the schedule for the network in question 2 with positive finishstart lags. Lag Trine deby between two activies. The defauk is FS b. [5 points] What is the duration of the project? c. [5 points] What is the critical Path? d. [5 points] What will happen if we add a 12-day lag between activities F and H. e. [5 points] What will happen if we keep part c and add eight (8) days of delay to activity C