Question: 6 4 . 3 ) Calculate the ES , EF , LS , and LF times and the slack for each activity in the figure
Calculate the ES EF LS and LF times and the slack for each activity in the figure below, and identify the critical path for the project. Can the project be completed in weeks?
Assume that Activity A actually finished at weeks and Activity B actually finished at weeks. Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule?
Table template:
tableActivityEDESEFLSLFTSAF
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
