Question: 6 4 . 3 ) Calculate the ES , EF , LS , and LF times and the slack for each activity in the figure

64.3) Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project. Can the project be completed in 30 weeks?
Assume that Activity A actually finished at 5 weeks and Activity B actually finished at 5 weeks. Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule?
Table template:
\table[[Activity,ED,ES,EF,LS,LF,TS,AF],[,,,,,,,],[,,,,,,,],[,,,,,,,]]