Question: 6 5 10 B Path A-B-D - 25 11 5 15 1 5 5 16 15 30 Start A D Finish 1 0 5 16

6 5 10 B Path A-B-D - 25 11 5 15 1 5 5 16 15 30 Start A D Finish 1 0 5 16 0 30 6 10 15 Path A-C-D - 30 C (Critical Path) 6 0 15 KEY Activity Early Early Node Start Duration Finish Activity Name Late Total Start Finish NOTE: This example uses the accepted convention of the project Critical Path Link starting on day 1 for calculating start and finish dates. There are Non-Critical Path Link other accepted conventions that may be used