Question: [ 6 : 5 9 PM , 3 / 6 / 2 0 2 4 ] komol vai Semo: An order for 5 0 0

[6:59 PM,3/6/2024] komol vai Semo: An order for 500 of a product is processed on operation A and operation B. The setup time on A is 50 minutes, and the run time per piece is 6 minutes. The setup time on B is 30 minutes, and the run time is 4 minutes per piece. It takes 30 minutes to move a lot between A and B. Since this is a rush order, it is given top priority and is run as soon as it arrives at either workstation. The total manufacturing lead time for processing these 500 pieces is:
75.17 hours
None of the above
85.17 hours
55.17 hours