Question: 6 . A CS&F Quality Team is investigating reducing the SMED for sweet production. The cleaning time for the boilers has been identified as a

6.
A CS&F Quality Team is investigating reducing the SMED for sweet production. The cleaning time for the boilers has been identified as a major time bottleneck. To reduce this two alternatives have been identified:
Three new boilers could be purchased so that they could be prepared before shutting down the line
Three used (second hand) boilers could be procured and refurbished instead. Refurbished boilers are considerably cheaper than new units but will take longer to acquire, also, there are concerns that the second-hand boilers may not be economically viable to refurb and the cost of ownership could be greater in the long term, when compared against brand new boilers
The information used by the team to establish which is the best way forward is shown on the following table:
Project Estimated
Savings
Probability
of success
Estimated
Cost
Estimated
Duration
1. Purchase
new boilers
750K
95%
90K
2 months
2. Purchase
and
refurbishment
of second
hand boilers
750K
75%
30k
5 months
Based on the above table and your understanding of Lean 6 Sigma, which ONE of the following statements is correct?
(PPI = Pareto Priority Index)
3 marksQuestion 6Select one:
Project 2 should be selected as it has the lower PPI
Project 1 should be selected as it has the higher PPI
Project 1 should be selected as it has the higher risk
Project 2 should be selected as it has the least risk
Project 2 should be selected as it has the higher PPI

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!