Question: 6. A robot is used for loading and unloading of parts to automated flexible machines. Loading time is 1 minute: unloading time is 1.5 minutes;

6. A robot is used for loading and unloading of

6. A robot is used for loading and unloading of parts to automated flexible machines. Loading time is 1 minute: unloading time is 1.5 minutes; machining time 15 minutes; Robot travel time between the machines including the inspection time is 3 minutes. Cost of robot (=30 TL/Hour; cost of machines C2=40 TL/Hour. How many machines (integer number) should be assigned to the robot so that the total robot and machine costs per cycle are minimized? 6 0 5 a) b) c) d) e) 4 3 2 Leave blank