Question: 6) All units in weeks Activity Predecessor Optimistic Most likely Pessimistic Time Time Time A S 3 4 5 B T 2 2 2 D
6) All units in weeks
Activity Predecessor Optimistic Most likely Pessimistic
Time Time Time
A S 3 4 5
B T 2 2 2
D A 1 5 9
M U 3 5 7
O B 1 2 9
P D, M, Y 8 10 12
R T 5 6 10
S T 1 2 3
T -- 4 4 4
U R 1 1 1
Y O 5 10 15
1. What is the critical path and expected completion date if you start this project on October 1st 2018?
2. What is the probability that you will finish this project 2 weeks earlier than your expected time?
Please answer both questions. Show work for understanding. Thank you !