Question: 6. Below is a project WBS with cost apportioned by percents. If the total project cost is estimated to be $600,000, what are the estimated

6. Below is a project WBS with cost apportioned
6. Below is a project WBS with cost apportioned by percents. If the total project cost is estimated to be $600,000, what are the estimated costs for the following deliverables? Router systems project Cost: $600,000 Definition 10% Design 40% Implementation 50% Objectives Requirements In-house testing 40% Customer testing & review 10% Inputs 3% Outputs 3% Files 4% Interfaces 10% Programming 20% a. Design? b. Programming? c. In-house testing