Question: 6 . Following a failed test on site, the Supervisor notifies a Defect. The Contractor disagrees. Due to the uncorrected Defect, the Project Manager cannot

6. Following a failed test on site, the Supervisor notifies a Defect. The Contractor disagrees. Due to the uncorrected Defect, the Project Manager cannot issue a certificate for Completion. As a result of the delay, delay damages incur. The Contractor strongly disagrees and refers the matter to the Adjudicator for a decision. The tribunal under the contract is arbitration.
Which TWO of the following statements are correct?
A dispute arising from a Supervisors notification of a Defect cannot be referred to the Adjudicator.
Where Option W2 applies, the Contractor may refer a dispute to the Adjudicator at any time whether or not the dispute has been referred to the Senior Representatives.
Where Option W1 applies, the Contractor should refer the dispute to the Senior Representatives before issuing a notice of adjudication.
Where Option W2 applies, the Contractor should refer the dispute to the Senior Representatives before referring to the tribunal.
Where Option W1 applies, an action or inaction of a Supervisor cannot be referred to a Senior Representatives.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!