Question: 6 . Following a failed test on site, the Supervisor notifies a Defect. The Contractor disagrees. Due to the uncorrected Defect, the Project Manager cannot
Following a failed test on site, the Supervisor notifies a Defect. The Contractor disagrees. Due to the uncorrected Defect, the Project Manager cannot issue a certificate for Completion. As a result of the delay, delay damages incur. The Contractor strongly disagrees and refers the matter to the Adjudicator for a decision. The tribunal under the contract is arbitration.
Which TWO of the following statements are correct?
A dispute arising from a Supervisors notification of a Defect cannot be referred to the Adjudicator.
Where Option W applies, the Contractor may refer a dispute to the Adjudicator at any time whether or not the dispute has been referred to the Senior Representatives.
Where Option W applies, the Contractor should refer the dispute to the Senior Representatives before issuing a notice of adjudication.
Where Option W applies, the Contractor should refer the dispute to the Senior Representatives before referring to the tribunal.
Where Option W applies, an action or inaction of a Supervisor cannot be referred to a Senior Representatives.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock