Question: 6 points so QUESTION 11 Problem #1: The data related to the activities of a project are given in Table 1. Show the calculations in

 6 points so QUESTION 11 Problem #1: The data related to
the activities of a project are given in Table 1. Show the
calculations in three tables, the Forward Pass Table, the Backward Pass Table
and the Critical Activity identification Table. Then answer questions 1 through 22.
ABCD E -ABB Activity Immediate Predecessors Activity Time (days) Table 1 F

6 points so QUESTION 11 Problem #1: The data related to the activities of a project are given in Table 1. Show the calculations in three tables, the Forward Pass Table, the Backward Pass Table and the Critical Activity identification Table. Then answer questions 1 through 22. ABCD E -ABB Activity Immediate Predecessors Activity Time (days) Table 1 F G H 11 UK DE A, E CF GG H1 9 467 9 6 17 6 4 98 What is the earliest finish time of activity D? QUESTION 12 6 points Save A Refer to the problem in question 11. What is the earliest finish time of activity E? QUESTION 13 6 points Save an Refer to the problem in question 11 What is the earliest finish time of activity QUESTION 14 6 points Save Answer Refer to the problem in question 11 What is the earliest finish time of activity K? QUESTION 15 6 points Save Answer Refer to the problem in question 11. What is the latest start time of activity B? QUESTION 16 6 points Save Answer Refer to the problem in question 11 What is the latest start time of activity C? QUESTION 17 6 points Save Answer Refer to the problem in question 11 What is the latest start time of activity D7 QUESTION 18 7 points Save Anne Refer to the problem in question 11 What is the latest start time of activity E? QUESTION 19 7 points Save Aswer Refer to the problem in question 11 What is the latest start time of activity F? QUESTION 20 7 points Save Answer Refer to the problem in question 11 What is the latest start time of activity G? QUESTION 21 7 points Save Ante Refer to the problem in question 11. What is the latest start time of activity H? QUESTION 22 7 points Refer to the problem in question 11 What is the slack of activity A2 QUESTION 23 7 points Save Answer Refer to the problem in question 11. What is the lack of activity B2 QUESTION 24 7 points Save Answer Refer to the problem in question 11 What is the lack of activity C QUESTION 25 7 points Save Answer Refer to the problem in question 11 What is the slack of activity D? QUESTION 26 7 points Save Anne Refer to the problem in question 11 What is the lack of activity ? QUESTION 27 7 points Save Answer Refer to the problem in question 11 What is the stack of activity QUE TUNZO 7 points SV Arwel Refer to the problem in question 11. What is the slack of activity H? QUESTION 29 7 points Save Answer Refer to the problem in question 11 What is the slack of activity QUESTION 30 7 points Save Answer Refer to the problem in question 11 What is the lack of activity QUESTION 31 7 points Save Antw Refer to the problem in question 11 What is the length of the critical path QUESTION 32 7 points Save Answer Refer to the problem in question 11 What is the number of activities on the critical path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!