Question: 6. Torque Manufacturing forecasts that its production will require 800,000 tons of bauxite over its planning period (365 days). Demand for Torque's products is stable
6. Torque Manufacturing forecasts that its production will require 800,000 tons of bauxite over its planning period (365 days). Demand for Torque's products is stable over time. Ordering costs amount to an average of $17 per order. Holding costs are estimated at $1.47 per ton of bauxite. The EOQ for Torque is _____ tons.
what is the total annual cost of inventory?
if it takes 7 days to receive an order from suppliers, at what inventory level should anther order be replaced?
Step by Step Solution
There are 3 Steps involved in it
The Economic Order Quantity EOQ for Torque Manufacturing is calculated using the formula EOQ 2DS H w... View full answer