Question: 6. Two projects are presented to the project selection committee. Project A will cost $250,000 to implement and is expected to have annual net cash

6. Two projects are presented to the project selection committee. Project A will cost $250,000 to implement and is expected to have annual net cash flows of $75,000. Project B will cost $150,000 to implement and should generate annual net cash flows of $ 52,000. Using the payback period method which project is better? Show your work or no credit will be given