6. Using the table below create a digraph to represent this project.
\table[[Task,Time Required,Precedents],[T1,8,],[T2,7,],[T3,5,],[T4,3,T1,T2],[T5,10,T1,T2],[T6,3,T3],[T7,4,T4],[T8,6,T4,T6],[T9,4,T5]]
7. Creat a Decreasing Time Priority List from the diagraph you created above for this project.
8. Schedule the project from the table in problem #6, using the Priority List from the Problem #7 with two processors.