Question: 6 Wagons are assembled in a process with a single resource. There are two types of wagons. The resource's processing time for the first type
Wagons are assembled in a process with a single resource. There are two types of wagons. The resource's processing time for the first type is 170 minutes and demand for this type is 2.4 wagons per hour. The resource's processing time for the second type is 38 minutes and demand for this type is 2.9 wagons per hour. There are 14 workers at this resource. Instruction: Round your answer to one decimal place, What is the implied utilization (%) of this resource? %