Question: 6 . with reactive crashing ( compared to pro - active crashing ) a . the tradeoff between cost and time changes, and the same
with reactive crashing compared to proactive crashing
a the tradeoff between cost and time changes, and the same time savings can be achieved at lower cost
b the project manager needs to develop decisonpoints where the contigency crashng plan will be implemented based on project status.
c the project status manager needs the ability to rellocated resources on short notices
d all of the above
We assumed in Q that duration of B might be or with equal likelihood. If duration of B is with chance and with chance, then the value of flexibility
a increases
b decreases
c remain the same
We assumed in Q that duration of B might be or with equal likelihood. If duration of B is with chance and with chance, then the value of flexibility
a increases
b decreases
c remain the same
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock