Question: 6.16. complete the following table to determine the run sequence for each of the sequencing rules. Job Process time Arrival date Due date Operation due

6.16. complete the following table to determine the run sequence for each of the sequencing rules. Job Process time Arrival date Due date Operation due date Sequencing rule

process time arrival time due date operation due date sequencing rule FCFS EDD ODD SPT

A 5 123 142 132

B 2 124 144 131

C 3 131 140 129

D 6 132 146 135