Question: 6.25 pts Compute the IRR statistic for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your
6.25 pts Compute the IRR statistic for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Should the project be accepted or rejected? Project E Year 0 2 3 4 5 Cash flow -$3,600 $1,110 $1,050 $900 $680 $480 o 7.52%, accepted O 7.52%, rejected 6.41%, accepted 6.41%, rejected