Question: The team's velocity has been 20 story points/sprint. They have 200 points remaining in the backlog for this release. The sprint length is two weeks.
The team's velocity has been 20 story points/sprint. They have 200 points remaining in the backlog for this release. The sprint length is two weeks. How many more weeks will it take to complete the release?
Step by Step Solution
3.31 Rating (151 Votes )
There are 3 Steps involved in it
Calculate the number of additional sprints needed Divide the remaining backlog points 200 ... View full answer