Question: 68) In a software development project, if the developers could start fixing bugs two days after the testers begin testing, this arrangement implies a. A

68) In a software development project, if the developers could start fixing bugs two days after the testers begin testing, this arrangement implies

a.

A start-to-start relationship with a 2-day lag

b.

A start-to-finish relationship with a 2-day lag

c.

A start-to-start relationship a 2-day lead

d.

A start-to-finish relationship with a 2-day lead

69) Which two of the following skills are most helpful for a PM when it comes to influencing the organization ?

a.

Procurement and communications

b.

Communication skills and a positive atitude

c.

Effective listening and active listening

d.

Organization and memory recall

70) Which of the following estimating techniques is often used to estimate a value when there is limited amount of detailed information about the project?

a.

Three-point estimating

b.

Analogous estimating

c.

Parametric estimating

d.

Bottom-up estimating

71) The project manager and the project team have decided to create a web page so the project stakeholders, both public and external, can access information, watch videos, and even e-mail the project team. What type of communication is the project web site?

a.

Interactive

b.

Push

c.

Pull

d.

Push-Pull

72) What type of communication is the web site that hosts project information?

a.

Push

b.

Push-Pull

c.

Pull

d.

Interactive

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!