Question: 68) In a software development project, if the developers could start fixing bugs two days after the testers begin testing, this arrangement implies a. A
68) In a software development project, if the developers could start fixing bugs two days after the testers begin testing, this arrangement implies
a.
A start-to-start relationship with a 2-day lag
b.
A start-to-finish relationship with a 2-day lag
c.
A start-to-start relationship a 2-day lead
d.
A start-to-finish relationship with a 2-day lead
69) Which two of the following skills are most helpful for a PM when it comes to influencing the organization ?
a.
Procurement and communications
b.
Communication skills and a positive atitude
c.
Effective listening and active listening
d.
Organization and memory recall
70) Which of the following estimating techniques is often used to estimate a value when there is limited amount of detailed information about the project?
a.
Three-point estimating
b.
Analogous estimating
c.
Parametric estimating
d.
Bottom-up estimating
71) The project manager and the project team have decided to create a web page so the project stakeholders, both public and external, can access information, watch videos, and even e-mail the project team. What type of communication is the project web site?
a.
Interactive
b.
Push
c.
Pull
d.
Push-Pull
72) What type of communication is the web site that hosts project information?
a.
Push
b.
Push-Pull
c.
Pull
d.
Interactive
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts