Question: 6.9. (LO 6.1) Soft Key is trying to determine how best to produce its newest product, DVORK keyboards. The keyboards could be produced in-house using
6.9. (LO 6.1) Soft Key is trying to determine how best to produce its newest product, DVORK keyboards. The keyboards could be produced in-house using either Process A or Process B, or purchased from a supplier. Cost data are given below. For what levels of demand should each process be chosen?
| Fixed Cost | Variable Cost | |
| Process A | $ 8,000 | $10 |
| Process B | $ 20,000 | $ 4 |
| Supplier | $ 0 | $ 20 |